Your GPU MSA Is a Loan, Not a Subscription: Why 48 B300s for 3 Years Is $6.3 Million You Owe Even If You Stop Using Them
A GPU capacity MSA is titled as a services agreement and works like a loan. The term is fixed, the monthly fee is owed whether or not you use the GPUs, there is no right to cancel, and 20% to 40% is paid up front. On 6 nodes of B300 GPUs (48 GPUs) at $5 per GPU-hour for 3 years, that is $6.3 million committed on signing. Before you sign one, underwrite the provider the way its lender underwrote you.
The founders signing these contracts are building products, not balance sheets, and the contract does not care
The companies buying GPU capacity today are young. A video generation startup replacing videographers, a robotics lab training manipulation models, an inference company serving a model it did not train, a seed-stage lab with a $20 million round and a 6-node reservation. Most are 1 to 3 years old, have never signed a contract larger than their lease, and read the document in front of them as what its title says: a Master Services Agreement.
The name is accurate about the service and silent about the money. The money terms in a GPU capacity MSA are the terms of a loan, and the rest of this guide reads them that way.
Three contract terms are three loan terms: a fixed amortization schedule, a down payment and a prepayment penalty
A take-or-pay contract is one in which the customer commits to paying for a minimum specified amount of services or usage over the term, which is how CoreWeave's S-1 defines the term for its own customer contracts. Three features follow from it.
| Loan term | How it appears in a GPU capacity MSA |
|---|---|
| Fixed amortization schedule | A 1, 2 or 3-year term with a monthly fee owed for every month, often billed in advance, whether you use the GPUs or not |
| Down payment | A prepayment of 20% to 40% of total contract value wired before delivery, often credited against the last months of the term (after month 24 in IREN's Microsoft contract) |
| Prepayment penalty | No termination for convenience; if you stop paying, the provider can terminate and claim the fees for the rest of the term, and keep the prepayment |
Public filings show the pattern. The SharonAI and ESDS master services agreement filed with the SEC covers 8,208 NVIDIA B300 GPUs on a 7-year initial term, states that "neither Party may terminate this MSA or any Service Order for convenience," requires quarterly payments in advance, and carves the customer's obligation to pay fees and advances out of the liability cap. IREN's $9.7 billion GB300 contract with Microsoft includes a 20% prepayment. Soluna's 36-month, $34.0 million agreement with HPE required $10.3 million up front, about 30%.
Hyperscalers sell the same structure in smaller units. AWS says EC2 Reserved Instances save up to 72% against on-demand pricing on 1-year or 3-year terms, and its Capacity Blocks for ML are charged up front and "cancellations aren't allowed." The discount is what you are paid for lending the provider certainty.
The 3-year discount saves $1.3 million if you use every hour and costs $4.2 million if you need to stop at month 12
Take a provider quoting $6 per GPU-hour on a 1-year term, $5.50 on 2 years and $5 on 3 years as an example, for a cluster of 48 B300 GPUs (6 nodes of 8). The longer term is cheaper per hour and larger in total.
| Term | $/GPU-hour | Annual cost | Total commitment | 30% prepayment | Fees still owed if you stop at month 12 |
|---|---|---|---|---|---|
| 1 year | $6.00 | $2.5M | $2.5M | $0.76M | $0 |
| 2 years | $5.50 | $2.3M | $4.6M | $1.4M | $2.3M |
| 3 years | $5.00 | $2.1M | $6.3M | $1.9M | $4.2M |
Three consecutive 1-year contracts at $6 cost $7.6 million. One 3-year contract at $5 costs $6.3 million. The 3-year deal saves $1.3 million over three years, and only if your model, product and funding still need 48 B300s in month 36. If any of those changes at month 12, you hold $4.2 million of fees for GPUs you no longer need.
Founders should price the term against their own runway. A startup with 18 months of cash signing a 36-month take-or-pay contract has committed its next round, and its investors' money, before raising it.
The MSA is written this way because the provider's lender underwrote your payments, not the provider's
GPUs are financed, and the financing is secured by your contract. CoreWeave's 2025 annual report states that it "primarily finance[s] our infrastructure development through asset-level debt supported by take-or-pay customer contracts," with committed contracts of approximately five years' weighted-average duration at December 31, 2025. In May 2026 it closed a $3.1 billion delayed draw term loan at SOFR plus 4.50% to fund infrastructure dedicated to contracts with two customers. SemiAnalysis reports that lenders generally need a long-term offtake contract, most often 5 years on take-or-pay terms, or an investment-grade backstop before lending to a neocloud, and size the loan so that contracted cash flow covers debt service by at least 1.3 times in the early years.
That is why the terms are not negotiable in the way a SaaS subscription is. A lender that has sized a loan on your monthly fee cannot let you cancel it. The no-termination-for-convenience clause, the payments in advance, the prepayment and the carve-out of your payment obligation from the liability cap are the lender's conditions passed through to you.
What you owe if you walk: the remaining fees, less whatever the provider resells, and the prepayment is gone
Under a take-or-pay MSA, stopping payment is a breach, not a cancellation. The usual sequence is a cure period (15 days to remedy non-payment in the SharonAI and ESDS agreement, which also treats a 30-day suspension as an irremediable breach; other agreements run 30 to 45 days), then suspension, termination and a claim for the fees for the rest of the term. Some MSAs give the provider a duty, or a right, to resell the freed capacity and credit the proceeds against what you owe. In a soft market the credit is small.
On the 3-year example above, stopping at month 6 looks like this: you have paid the $1.9 million prepayment plus 6 monthly fees of $175,200, $2.9 million in total, and the provider's claim is the remaining 30 months, $5.3 million, less resale proceeds. The prepayment does not offset the claim where the MSA applies it to the final months of the term, as IREN's Microsoft contract does after month 24, because those are months you will never reach.
Take-or-pay minimums are drafted as the price of reserving capacity, not as damages for breach, which is what makes them hard to attack as an unenforceable penalty. Do not plan on a court rescuing you from the number you signed.
Your prepayment is an unsecured loan of $1.3 million to $2.5 million that the provider can spend on day one
The down payment is the part founders feel least and risk most. A 20% to 40% prepayment on the $6.3 million example is $1.3 million to $2.5 million, wired before a single GPU-hour is delivered. Unless the MSA puts it in escrow or behind a bank letter of credit, it is the provider's cash the moment it lands: it funds the GPU purchase order, the colocation deposit, or last month's payroll.
If the cluster underperforms in month 2, is breached, or never comes up, your remedy is a claim against a company that has already spent your money. If the provider files for bankruptcy, it can ask the court to reject your MSA and the unused prepayment becomes a general unsecured claim. When hosting provider Compute North filed for Chapter 11 in 2022, Marathon had $50 million in deposits and prepayments with it, recorded a $55.7 million impairment and accepted a $40 million general unsecured claim. Our guide to GPU prepayment risk covers the six ways a prepayment is lost and the documents that stop each one.
A bank lending $2 million would run diligence first. The three checks below are that diligence, done from the buyer's side.
CHECK 1 OF 3
Check 1: The people running the cluster decide whether month 2 is a working product or a locked-up deposit
A 6-node B300 cluster has to be racked, cabled, burned in, tuned and operated by people who have done it before. A provider that has not can take months to deliver stable capacity, and you will be paying $175,200 a month while it learns. Delivery delays reach the top of the market: in November 2025, CoreWeave cut its revenue forecast after delays at a data center partner. A 30-person provider holding your deposit has less room to recover.
Security is the other half. Your training data, fine-tuning sets and model weights sit on the provider's storage and network. A breach at the provider is a breach of your core asset, and a take-or-pay MSA keeps you paying through it.
Ask for: named references for a comparable cluster the provider has brought up, with dates and GPU counts; the resumes of the people who will operate your cluster; the OEM purchase order or delivery confirmation and a serial-number schedule for your nodes; a current SOC 2 Type II report or ISO 27001 certificate covering the environment hosting your workload; the provider's incident history for the last 24 months; and a written acceptance test (node count, interconnect throughput, sustained utilization over a defined burn-in period) that must pass before the first monthly fee is due.
CHECK 2 OF 3
Check 2: A provider with under 6 months of runway can fail inside your term, and your prepayment may be what keeps it alive
A 2-year contract is a 2-year bet that the provider stays in business. Public companies show how fast that bet can go wrong. On October 27, 2022, Core Scientific, then one of the largest listed bitcoin miners and hosting providers, disclosed that "existing cash resources will be depleted by the end of 2022 or sooner," that "substantial doubt exists about the Company's ability to continue as a going concern," and that it would not make payments due in late October and early November. It filed for Chapter 11 on December 21, 2022, 55 days later.
Now put a prepayment next to that balance sheet. Suppose a listed GPU provider has a going-concern paragraph in its auditor's report and $600,000 of cash against $400,000 of monthly operating costs, under two months of runway. A 30% prepayment on a $4.2 million 2-year contract for 6 nodes is $1.26 million. Your wire would triple the provider's cash balance. You would not be buying capacity; you would be its bridge financing, unsecured, with no board seat and no covenants. A buyer who reads the auditor's report before wiring can decline that deal. One who reads only the MSA cannot see it.
Ask for: financial viability as a named step in your due diligence, run before the prepayment is wired and before the MSA is signed. Most founders check the GPUs and the price and never look at the company behind them. Have a lawyer who works on compute transactions run this part; what to request and how to read it depends on the provider, and the cost of the review is a rounding error against the prepayment.
CHECK 3 OF 3
Check 3: The colocation facility, not the provider, decides whether your uptime SLA is real
The provider's uptime commitment depends on power, cooling and network it does not own. Those live in the colocation facility under a separate contract you have not seen. A 99.49% uptime SLA, taken as an example, allows about 44.7 hours of downtime a year, roughly 3.7 hours a month, before the provider owes you anything, and the usual remedy is a service credit against a future bill. If the facility gives the provider a weaker SLA than the provider gave you, the difference is your downtime, and under a take-or-pay MSA you keep paying through it.
Uptime Institute describes a Tier III facility as concurrently maintainable: any component can be shut down for maintenance without affecting IT operations. Buyers do not need a certificate to ask the questions the Tier framework asks. What matters for an inference workload with its own customer SLAs is whether a generator, a UPS string or a cooling loop can fail without taking your racks down.
Ask for: the colocation agreement between the provider and the facility, with a term at least as long as your MSA; the generator, UPS and cooling redundancy serving your racks, stated as N+1 or 2N; the facility's outage history for the last 24 months; the uptime SLA the provider receives from the facility, which must be at least as strong as the one it gives you; physical access controls and the facility's SOC 2 Type II report; and a non-disturbance agreement from the facility's landlord or lender so a dispute above the provider does not evict your cluster. Our guide to colocation red flags for AI infrastructure covers the full list.
Nine terms that make the loan work in both directions
A take-or-pay MSA protects the provider's lender. These terms protect you, and a provider that intends to deliver can sign them.
- Delivery date with an outside date. Capacity is accepted by a fixed date; if it is not, you may terminate and recover the full prepayment within a fixed number of days.
- Acceptance test before billing. The first monthly fee is due only after the cluster passes a written acceptance test. No billing for capacity that is not delivered.
- Prepayment in escrow or behind a letter of credit. Released against delivery and acceptance, applied to the final months of the term, so the provider never holds your money before it has earned it.
- Material breach triggers in numbers. Availability below a negotiated threshold for a negotiated number of consecutive months, a single outage longer than a negotiated number of hours, loss of the GPUs or the facility, or a security breach affecting your data, each lets you terminate and recover the unused prepayment.
- Early termination defined, with mitigation. If you must exit, the fee is a defined formula, the provider has a duty to resell the capacity, and resale proceeds reduce what you owe.
- Flex-down and transfer rights. The right to reduce committed capacity by a negotiated percentage after month 12, and to assign or sublicense your capacity to another customer.
- Back-to-back SLA. The provider's colocation SLA is at least as strong as yours, and the colocation term is at least as long as your MSA.
- Lender non-disturbance. The provider's GPU lender agrees in writing not to disturb your use of the GPUs while you are not in default, so a provider default does not become a repossession of your cluster under UCC § 9-609.
- Financial covenants and reporting. Quarterly financials from the provider during the term, notice of any going-concern qualification, debt default or change of control, and the right to terminate and recover the prepayment if one occurs.
The best structure puts your cluster, its financing and your MSA in a single-purpose entity, the approach CoreWeave's CEO calls the box, so your deal is insulated from the provider's other customers. Ask whether the provider offers it.
Frequently asked questions
What does take-or-pay mean in a GPU MSA?
Take-or-pay means the customer commits to paying for a minimum amount of capacity for the whole term whether or not it uses the GPUs. CoreWeave's S-1 defines it as a contract in which the customer commits to paying for a minimum specified amount of services or usage. In practice the monthly fee is owed for every month of a 1, 2 or 3-year term, and the MSA often gives the customer no right to terminate for convenience, as the SharonAI and ESDS agreement does.
What happens if I stop paying a GPU capacity contract early?
Under a take-or-pay MSA, stopping payment is a breach, not a cancellation. After a cure period, 15 days in the SharonAI and ESDS agreement and 30 to 45 days in others, the provider can suspend service, terminate and claim the remaining fees for the rest of the term, less whatever it recovers by reselling the capacity. Any prepayment is usually forfeited. On a 3-year contract for 48 B300 GPUs at $5 per GPU-hour, walking away at month 12 leaves about $4.2 million of fees still owed before mitigation.
Why are GPU MSAs structured like loans?
Because the provider's lenders are underwriting your payments. CoreWeave's 2025 annual report states that it primarily finances infrastructure development through asset-level debt supported by take-or-pay customer contracts. A lender sizing a GPU loan looks at the contracted cash flow from customers, so the MSA has to make that cash flow firm: a fixed term, no termination for convenience, payments in advance and an upfront deposit.
Is a 3-year GPU contract cheaper than a 1-year contract?
Per GPU-hour, yes. Hyperscalers publish the same trade-off: AWS says Reserved Instances save up to 72% against on-demand pricing on 1-year or 3-year terms. On a neocloud contract, taking $6 per GPU-hour on a 1-year term and $5 on a 3-year term as an example, 48 B300 GPUs cost $2.5 million a year on the 1-year deal and $2.1 million a year on the 3-year deal. The saving is $1.3 million over three years if you use every hour, and the price is $4.2 million of fees still owed if you need to stop at month 12.
How do I check whether a GPU provider can survive my contract term?
Make the provider's financial viability a named step in your due diligence, before the prepayment is wired and before the MSA is signed, and have a lawyer who works on compute transactions run it. A provider with under 6 months of runway can fail inside a 2-year term: Core Scientific warned on October 27, 2022 that its cash would be depleted by the end of 2022 or sooner and filed for Chapter 11 on December 21, 2022, 55 days later. A buyer who reads the auditor's report before wiring can decline that deal; one who reads only the MSA cannot see it.
What should I ask about the data center hosting my GPUs?
Ask for the colocation agreement between the provider and the facility, with a term at least as long as your MSA; the generator, UPS and cooling redundancy serving your racks, stated as N+1 or 2N; the facility's outage history for the last 24 months; the uptime SLA the provider receives from the facility, which should be at least as strong as the SLA it gives you; and the facility's physical security and SOC 2 Type II report. Uptime Institute describes a Tier III facility as concurrently maintainable, meaning any component can be shut down for maintenance without affecting IT operations.
Send LegalLayer the MSA before you wire the prepayment, and it will tell you what you are borrowing and from whom
LegalLayer reviews and negotiates GPU capacity contracts for the companies buying compute: AI labs, inference providers, robotics companies and generative media startups. That means the take-or-pay and early termination terms, the prepayment protections, diligence on the provider's operating record and financial viability, and the colocation terms behind the uptime commitment, with a licensed lawyer accountable for the work. If you are about to sign a 1, 2 or 3-year GPU MSA, start at legallayer.ai.
This article is general information, not legal, tax or financial advice. The $5 to $6 per GPU-hour pricing, the 6-node cluster and the going-concern provider are illustrative examples, not descriptions of a specific company or transaction. Figures for CoreWeave, SharonAI, IREN, Soluna, Core Scientific and Marathon reflect their public filings and announcements as of November 16, 2026. Consult qualified counsel on any specific transaction.
Sources
- CoreWeave, Form S-1 (March 2025), definition of take-or-pay: https://www.sec.gov/Archives/edgar/data/1769628/000119312525044231/d899798ds1.htm
- CoreWeave, Form 10-K for fiscal 2025: https://s205.q4cdn.com/133937190/files/doc_financials/2025/q4/CoreWeave-Inc-FY25-10-K-7.pdf
- CoreWeave, "CoreWeave Closes $3.1 Billion Loan Facility" (May 18, 2026): https://investors.coreweave.com/news/news-details/2026/CoreWeave-Closes-3-1-Billion-Loan-Facility-Expanding-Access-to-Public-Markets-for-GPU-Backed-Financing/default.aspx
- SharonAI Holdings, Exhibit 10.17, Master Services Agreement with ESDS (effective March 31, 2026): https://www.sec.gov/Archives/edgar/data/2068385/000149315226023769/ex10-17.htm
- IREN, "IREN Secures $9.7bn AI Cloud Contract with Microsoft" (November 3, 2025): https://iren.gcs-web.com/news-releases/news-release-details/iren-secures-97bn-ai-cloud-contract-microsoft
- Soluna Holdings, Form 8-K on the HPE agreement (June 2024): https://www.sec.gov/Archives/edgar/data/64463/000149315224024845/form8-k.htm
- AWS, EC2 Reserved Instances pricing: https://aws.amazon.com/ec2/pricing/reserved-instances/
- AWS, EC2 Capacity Blocks for ML documentation: https://docs.aws.amazon.com/es_en/AWSEC2/latest/UserGuide/ec2-capacity-blocks.html
- SemiAnalysis, "Nvidia GPU Debt Backstop Unleashes the AI Project Trinity": https://newsletter.semianalysis.com/p/nvidia-gpu-debt-backstop-unleashes
- 11 U.S.C. § 365 (executory contracts): https://www.law.cornell.edu/uscode/text/11/365
- UCC § 9-609 (secured party's right to take possession after default): https://www.law.cornell.edu/ucc/9/9-609
- Cointelegraph, "Marathon reports $80M exposure to bankrupt mining firm" (October 7, 2022): https://cointelegraph.com/news/marathon-reports-80m-exposure-to-bankrupt-mining-firm
- Marathon Digital Holdings, Form 10-K for fiscal 2023: https://www.sec.gov/Archives/edgar/data/1507605/000162828024007680/mara-20231231.htm
- BusinessDay (Reuters), "CoreWeave cuts revenue forecast on data centre delay" (November 11, 2025): https://www.businessday.co.za/world/international-companies/2025-11-11-coreweave-cuts-revenue-forecast-on-data-centre-delay/
- Core Scientific, Form 8-K (October 27, 2022): https://www.sec.gov/Archives/edgar/data/1839341/000119312522270236/d395956d8k.htm
- SiliconANGLE, "Bitcoin miner Core Scientific files for bankruptcy" (December 21, 2022): https://siliconangle.com/2022/12/21/bitcoin-miner-core-scientific-files-bankruptcy
- Uptime Institute, Tier Classification System: https://uptimeinstitute.com/tiers